Project No. | 13715 | ![]() |
Industry | Power Stations | |
Site | Germany | |
Implemetation | September 2010 | |
On 16th September the large load of the two silos will start at 8 p.m. from the KURZ factory premises in Brackenheim with direction Lauffen/Neckar. The silos have a diameter of 6,20 m with a length of 30 m. Each silo will be transported with a 8-platform lorry. At the Lauffen harbour the silos will go on board the inland water vessels.The trip on waterway will take 12 days on Neckar, Rhein, in the Netherlands on Ijssel, Princess Margriet-canal, Van Starkenborgh-canal and Ems-canal again in Germany on Weser, Mittelland-canal and Elbe-Havel-canal to the site. | ||
Scope of supply: 2 factory-welded large-volume silos Volume: 720 m³ Cylinder height: 21.500 mm Diameter: 6.200 mm Cone: 70° with breeches-type outlet |