Project No. | 12616 | ![]() |
Industry | Concrete | |
Installation site | Germany | |
Implementation | July 2006 - February 2009 | |
Europe’s largest concrete production facility: it reaches new dimensions with 900 m³ concrete per hour round the clock. Various grades of concrete just in time on site. This demands the highest reliability and quality of all plant components under these extreme conditions. KURZ is supplying the wagon unloading system and the silo systems. KURZ has been working on the project from the initial planning stage including transport, installation, commissioning and after-sales service. | ||
Scope of supply: 6 railway wagon unloading units with 17 docking stations with conveyor 2 site-bolted silos: Volume: 535 m³ Silo height: 12,000 mm Diameter: 7,000 mm 13 factory-welded silos: Volumes: 64 - 218 m³ Silo heights: 9,000 - 15,000 mm Diameters: 2,900 - 4,200 mm 4 compressor stations In transportable units of 110 kW each inc. compressed air drying, suitable for the site Pneumatic air conveyor station to supply all silos from the large storage silos (design throughput 90 t/h) including controller |